Painting Production Rates (2026) + Calibration Calculator
By Marco Cachi, CEO of Majotek. Last reviewed . Free, no signup. How we get our numbers
Interior production rates per painter-hour
| Surface | First coat | Each extra coat |
|---|---|---|
| Walls (smooth drywall, roll and cut) | 175 sq ft | 225 sq ft |
| Ceilings (flat, roll) | 125 sq ft | 160 sq ft |
| Baseboard trim (brush) | 40 lin ft | 40 lin ft |
| Doors (slab both sides + frame) | 0.75 hr per door | 0.75 hr per door |
Slow these down for occupied homes, heavy texture, high ceilings, dark-to-light color changes and detailed trim. See the methodology page for sources.
Calibrate from a finished job
How to track your own rates
- Measure each surface before the job (the estimate calculator does this per room).
- Have the crew log hours per surface type, not just per day. A note on the phone is enough.
- After the job, enter area, coats and hours above to get your real rate.
- Average three to five similar jobs before changing your bidding rates.
- Compare estimated against actual on every job with the job costing calculator.
Frequently asked questions
+What is a good production rate for painting walls?
For rolling and cutting in smooth interior drywall, 175 sq ft per painter-hour on the first coat and 225 sq ft on each later coat are reasonable starting points. Public guides disagree by 30% or more, so measure your own crew.
+Why is the second coat faster than the first?
The surface is already sealed and the color is already cut in, so the painter moves faster and uses less paint. Pricing every coat at first-coat speed overcharges; pricing the first coat at second-coat speed underbids.
+How do I find my crew's production rate?
After a job, note the measured area of each surface, the number of coats and the painter-hours spent on it. Divide area by hours, adjusting for faster later coats. The calculator on this page does that math.
+Do production rates include prep and setup?
No. Keep prep (patching, sanding, caulking, masking) and setup/cleanup as separate hours. Mixing them into the rate makes it swing wildly from job to job.